A conservatory base being laid in a UK back garden ahead of frame installation
Process & rules · Guide

How long does it take to build a conservatory?

Most conservatories are built in 2–6 weeks — but the groundworks, planning and manufacturing lead times add to the total.

Updated June 2026Sourced from trade and government guidance
CA
Conservatory Answers editorial
Reviewed against the Planning Portal, FENSA, the Glass & Glazing Federation and LABC building control.

The short answer

Once groundworks start, a typical uPVC or aluminium conservatory takes 2–5 working days to erect; total project time from order to completion is usually 6–12 weeks. The manufacturing lead time for bespoke frames accounts for most of the wait. Orangeries and structures requiring building regulations approval take longer. See conservatory base and foundations for the groundworks detail.

The question “how long does a conservatory take to build?” has two different answers depending on what you include. The on-site construction — laying the base, erecting the frame and fitting the glazing — is remarkably quick for most standard conservatories: typically 2–5 working days once everything is on site and the base has cured. But the total elapsed time from signing the contract to sitting in the finished conservatory includes a manufacturing and scheduling lead time that typically runs 6–10 weeks, plus the base cure time, any planning process and any delays from weather, access or material supply.

Build time at a glance

The manufacturing lead time

Most conservatory frames are manufactured to order by specialist factories, not held in stock. Once you sign a contract and pay a deposit, the dimensions and specification are sent to the factory for production. Standard uPVC frames from large national manufacturers typically have lead times of 4–8 weeks; bespoke or non-standard colours, large frames or aluminium systems may take 8–12 weeks. The installer then schedules the installation once the components have arrived and their groundwork team is available. This combined lead and scheduling time is why most conservatory companies quote 8–12 weeks from order to start of installation.

The groundworks and base

Before any frame goes up, the base must be prepared. For a simple concrete raft on flat ground, this typically takes 1–2 days to lay, followed by a curing period of 7–14 days before the frame crew arrives. A more complex base — a step-down to a lower garden level, a suspended floor on poor ground, or extensive drainage work — takes longer. See conservatory base and foundations for what is involved. Some companies programme the groundworks shortly before the frame arrives to minimise the gap; others let the base cure fully before scheduling the frame. Ask your installer how they programme the two stages.

StageTypical durationNotes
Survey and contract1–2 weeksIncludes detailed site measure
Manufacturing lead time6–10 weeksLonger for bespoke / aluminium
Groundworks & base1–3 daysPlus 7–14 days cure
Frame & glazing erection2–5 daysStandard uPVC conservatory
Finishing (sealant, cleaning)Half–1 dayUsually same day as completion
Orangery (masonry)4–8 weeks on siteMuch longer due to brickwork

What causes delays

Common causes of delay beyond the planned programme include:

Get dates in writing: a reputable installer will provide a programme with expected dates for manufacturing delivery, groundworks and installation in the contract. If yours does not, ask for one — it sets expectations and gives you a basis for recourse if significant delays occur. See how to choose a conservatory company for what to look for in a contract.

How to shorten the project time

There is limited scope to significantly shorten the manufacturing lead time, but a few practical steps help. Order early relative to the season you want to use the conservatory in — spring and summer are peak installation seasons, so ordering in autumn or winter typically gives shorter lead times. Confirm that the installer has all site measurements at the survey stage so there are no measurement queries that delay the factory order. Ensure good access to the rear of the property is available from day one. If you are taking time off work for the installation, confirm the schedule firmly in writing before booking leave — last-minute rescheduling by installers is a common frustration. This page provides general guidance only; timescales are typical illustrations based on trade guidance and will vary by installer, project and region.

Ready to plan your conservatory project?

Getting quotes from installers now — and confirming manufacturing lead times — lets you plan your project to be ready when you want it.

Free to use. No obligation. We are an independent guide, not an installer.

Frequently asked questions

How long does a conservatory take to build once work starts?

Once the base is laid and cured, erecting a standard uPVC or aluminium conservatory frame typically takes 2–5 working days. The total project time from order to completion is usually 8–14 weeks including manufacturing lead time.

How long does it take for a conservatory base to set?

A concrete raft base typically takes 7–14 days to cure before the conservatory frame is installed on top. The installer programmes this into the schedule.

How long does an orangery take to build?

Much longer than a conservatory, because of the masonry work. Most orangeries take 8–14 weeks on site from groundworks to completion, plus a manufacturing or materials lead time.

Can a conservatory be built in a week?

The frame erection of a small, simple conservatory can be completed in 2–3 days once the base is ready. But the base must cure first, and the total project from order to completion is typically 8–14 weeks.

Sources & further reading

This is general information about conservatories and orangeries in the UK, not planning, structural, legal or financial advice. Costs are typical illustrations only and are not quotes for any specific project; actual prices vary with size, site conditions and your chosen installer.